Anasayfa » Blog » When The Zoning Plan Is Canceled, It Cannot Be Found If The Construction Is Not Finished On Time

When The Zoning Plan Is Canceled, It Cannot Be Found If The Construction Is Not Finished On Time

General Assembly of Law 2017/845 E. , 2020/723 K.

“Justice Text”

COURT: Civil Court of First Instance

1. At the end of the trial due to the “compensation” lawsuit between the parties, the decision of the dismissal of the case given by the Alanya 4th Civil Court of First Instance was overturned by the 23rd Civil Chamber of the Court of Cassation upon appeal by the plaintiffs’ attorney, and the Court resisted the decision to reverse the Special Chamber.
2. The decision to resist was appealed by the plaintiffs’ attorney.
3. After being examined by the General Assembly of the Civil Procedure, it was understood that the decision to resist was appealed in due time, and as of the date of the decision to resist, the second article of the 438th article of the Code of Civil Procedure (HUMK) no. Since it is not foreseen to hold a hearing in the appeal examination of the decisions of resistance in the subsection paragraph, it was decided to reject the request of the plaintiffs’ attorney and after the documents in the file were read, the necessity was discussed:

I. TRIAL PROCESS
Plaintiff’s Claim:
4. In the petition of the plaintiffs’ attorney dated 22.11.2012; A construction contract was drawn up between the parties on 14.05.2005 in return for land share, that at least 24 flats will be given to the landowners from the construction to be made in accordance with the contract, that although the production of the flats that will fall to the defendant contractor has been completed, the independent sections falling to the plaintiffs have not been completed, in accordance with the construction contract signed between the parties in return for the land share, from the date of the construction license. Although the construction should be completed within 18 months from the date of the date, the construction is not finished, therefore the defendant has to pay a monthly delay penalty of 500 TL for each flat, the construction is also defective, the foundation has shifted, even though the defendant has given a warning to take over the buildings, the buildings do not meet the delivery condition. With the legal interest of 729.000 TL in total, 500 TL per month for each flat as of 17.10.2007, when the construction of 24 flats falling to the plaintiffs, without prejudice to their rights regarding the surplus, He also requested from the defendant that his collection be decided.
Response of the Defendant:
5. In the reply petition dated 17.12.2012, the attorney of the defendant; Due to the economic crisis in the country and force majeure, the construction could not be completed, the zoning obstacle still continues, the zoning application made in the region including the parcels where the construction is located was canceled with the decision of the administrative court, therefore, in the letter of the Municipality dated 18.03.2008, it was stated that the request for the construction visa was not taken into consideration. As a result of the determination made by the company, it was determined that the construction was completed before the mentioned date, the occupancy license could not be obtained due to force majeure due to the cancellation of the zoning application, the other reason for the actual delay was the request of the land owners for changes after the completion of the construction, the land owners did not receive their apartments even though the construction was actually completed, and the land that fell to the client that they did not transfer their shares, that the plaintiffs actually took over the flats, that they or their tenants began to live in the flats, He requested that the case be dismissed, stating that the A block slipped during the road work and that the A block was demolished with the decision of the council dated 22.11.2012 and the demolition process was carried out.
Court order:
6. With the decision of Alanya 4th Civil Court of First Instance dated 15.01.2014 and numbered 2012/663 E., 2014/6 K.; The zoning plan in the area where the parcels subject to the contract are located was canceled with the decision of the Antalya 2nd Administrative Court dated 05.04.2007 and numbered 2006/1919 E., 2007/527 K. In 2006, the construction permit was obtained, the 18-month construction period expired on 17.10.2007 from the date of receipt of the license, the construction period expired on 17.10.2007, and since the zoning plan in the area where the immovables were annulled by the administrative court during the construction period, all license procedures regarding the constructions in the said area were stopped by the municipality. The basic visa request for this issue was also rejected with the reply of the municipality dated 18.03.2008, despite the cancellation of the zoning plan in the area where the immovables are located, illegal construction was attempted by the plaintiff, within this framework, some buildings were built within the scope of the project, when all these issues are evaluated together, the zoning plan It was decided to reject the case on the grounds that no fault could be attributed to the defendant in the cancellation of the construction plan, that the cancellation of the zoning plan could not be predicted by the defendant beforehand, that it was impossible to continue the construction as a license could not be obtained in a place where the zoning plan was cancelled, and that the defendant could not be held liable for the penal clause because the construction was not completed on time. .
Special Chamber Ruling Decision:
7. Take

anya filed an appeal against the above-mentioned decision of the 4th Civil Court of First Instance by the plaintiffs’ attorney in due time.
8. With the decision of the 23rd Civil Chamber of the Supreme Court dated 20.01.2015 and numbered 2014/6179 E., 2015/310 K.;
“…According to the construction contract in return for the land share between the parties, it has been decided that the construction in question will be delivered to the land owners by obtaining the construction license within 6 months from the date of the contract and by obtaining the preliminary occupancy certificate within 18 months from this date. The construction license for the construction was obtained on 17.04.2006, and the plaintiff landlords accepted that the construction period would start from this date, and claimed that the independent sections were not delivered at the end of the 18-month period and demanded the collection of delay compensation. In the article titled “duration of construction” of the contract, it was stated that the municipality could add to the duration of the work provided that the construction was stopped due to the tourism ban. It is clear that no additions can be made. In that case, essentially, the work must be delivered 18 months after the construction permit date, that is, on 17.10.2007.
The court accepted that the period was extended due to the cancellation of the zoning plan in the area where the construction was carried out, and therefore the contractor did not default on the delivery, and the case was dismissed. However, it is examined whether a time will be added to the date that should be delivered on 17.10.2007, which was determined just above, due to the overproduction claimed by the contractor in his defense, and if there is, on the basis of the date to be found by adding this period, otherwise, on the basis of 17.10.2007, the zoning plan will be prepared from this date. While a decision should be made by evaluating whether the cancellation of the zoning plan will affect its responsibility pursuant to Article 102/2 (TBK 119/2) of the BK, in the event that it is canceled later, that is, after the contractor defaults on delivery, it was wrong not to take these issues into consideration.
In addition, in accordance with the contract, it was decided that 24 independent sections would be given to the plaintiff land owners on the plot of plot no. 1515, and it was argued that these independent sections were started to be saved by the land owners by renting them out or living them. As a matter of fact, various lease agreements have been submitted to the file as evidence in this regard. As it is known, the claim for delay compensation, which is the subject of the lawsuit, in principle means the damage actually suffered. In this case, if it is determined that the contractor has defaulted on delivery as a result of the investigation to be carried out in accordance with the above paragraph, it is obligatory to investigate the date on which each independent section was delivered to the land owners and to reach a conclusion accordingly.
Likewise, it is understood from the information and documents in the file that the A block, which has no dispute that it belongs to the landowners, was demolished, and it was argued that the blocks containing the other independent sections should be strengthened and that it was uninhabitable. If it is determined that there is a fault of the contractor by examining whether there is a fault of the contractor or not and the reason, an evaluation should be made in this direction.
The decision was overturned on the grounds that it was against the procedure and the law to make a decision without considering the aforementioned issues, and the verdict had to be reversed for these reasons.
Decision to Resist:
9. With the decision of Alanya 4th Civil Court of First Instance dated 10.07.2015 and numbered 2015/190 E., 2015/439 K.; In accordance with Article 28/1 of İYÜK numbered 2577, 30 days from the date of notification of the court decisions of the administration, the zoning plan in the area where the subject property is located was canceled by the decision of the administrative court, the decision was notified to the municipality on 31.05.2007, the decision was approved and finalized by the Council of State upon appeal. The municipality has to implement the decision until 30.06.2007 as of the notification of the decision, the construction completion date of the defendant is 17.10.2007 and the zoning plan for the area where the construction is located is canceled before the completion of the construction period and the municipality has to implement the decision of the administrative court. According to Article 102/2 of the repealed Code of Obligations No. 818 (BK), it was decided to resist on the grounds that the defendant was not at fault in the default due to the failure to complete the construction on time.
Appeal of the Decision to Resist:
10. The decision of resistance was appealed by the plaintiffs’ attorney within the time limit.

II. DISPUTE
11. Dispute brought before the General Assembly of Law through resistance; In the concrete case, in accordance with the construction contract in return for the land share signed between the parties, whether the defendant contractor is in default in delivery, if the contractor is deemed to be in default,

It is gathered at the point of whether the researches specified in the Ozma decision should be carried out.

III. REASON
12. For the resolution of the dispute, it is beneficial to first examine the legal regulations related to the subject.
Article 102 of the UK No. 818 titled “Liability in case of accident”:
“The defaulting debtor is obliged to pay for loss and damage due to the performance of the debt, and is also liable for accidental damage.
The debtor can be relieved of this liability by proving that he has committed one day without fault or that the accident will hit the thing to be paid to the detriment of the creditor, even if the debt is fulfilled on time and on time.”
It is arranged in the form.
13. The debtor in default is subject to Article 102/I of the UK No. 818. According to the article, he is also held liable for “accidental damage”. The term “accident” is used here in a broad sense. All the reasons that arise during the default without the fault of the debtor and make performance impossible are also included in the concept of “accident” (Akman, S./ Burcuoğlu, H./ Altop, A.: Tekinay Law of Obligations General Provisions, Istanbul 1993, p. 926).
14. As a rule, if performance becomes impossible for a reason that arose without the fault of the debtor, the debtor is relieved of his debt (BK art. 117). However, in the event that the perfect impossibility arises after the default, this rule is not applied and the debtor is now held responsible even for the accident.
15. 102/II of the UK No. 818. The article provides two possibilities for the debtor to avoid liability for the accident. The debtor can prove that he was in default without any fault or that even if the debt was fulfilled on time, the debtor would have been in an accident to the detriment of the creditor. For this reason, if the debtor has been in default without fault, proving this is sufficient to eliminate the liability due to the accident. The point to be considered here is whether the debtor is at fault only in default. (Akman, S. / Burcuoğlu, H. / Altop, A.: p. 927).
16. Even if the debtor is at fault in default, he can avoid liability by taking advantage of a second proof. Indeed, the debtor has the right to prove that even if the debt were performed on time, the object of the debt would have inadvertently incurred to the detriment of the creditor.
17. In order for the aforementioned burden of proof to be considered fulfilled, if the object of the debt had been given to the creditor, it must be fixed that he would have suffered an accident as well, and he must also prove that the creditor would incur losses from the accident even if the performance was made on time. In the event that these two conditions are fulfilled, the debtor will be able to avoid liability even if he is at fault in default (Akman S./ Burcuoğlu H./ Altop A.: p. 927).
18. When the concrete event is evaluated in the light of these principles and explanations; A construction contract was signed between the land owner, claimants and the contractor on 14.06.2005 in return for land share, and the duration of the construction is 18 months from the date of the license, provided that the construction license is obtained within 6 months from the contract date, the construction is stopped by the municipality due to tourism ban or war, earthquake, mobilization. It has been decided that if the construction is stopped due to unforeseen reasons, the elapsed time will be added to the construction period, and if the construction is not completed on time, the contractor will pay the landlords a monthly rent of 500 TL for each flat.
19. According to the letter of the Alanya Municipality Directorate of Development and Urbanization dated 21.01.2013 and the building permit included in the file, the construction permit was given on 17.04.2006, and the construction should be completed on 17.10.2007 according to the contract.
20. In the letter of Alanya Municipality Directorate of Zoning Affairs dated 18.03.2008, it was stated that the basic visa request of the contractor related to the construction subject to the lawsuit could not be evaluated due to the cancellation of the zoning application in the region with the decision of the Antalya 2nd Administrative Court.
21. In the letter of Alanya Municipality Directorate of Development and Urbanization dated 16.07.2013, which is included in the file, it is stated that the occupancy permit certificate could not be given to the buildings built on the parcel subject to the lawsuit, due to the cancellation of the zoning application in the region.
22. With the decision of the Antalya 2nd Administrative Court, dated 05.04.2007 and numbered 2006/1919 E., 2007/527 K., it was decided to cancel the zoning application made in the region where the parcels subject to the construction contract in return for land share are located. It was approved by the decision of the 6th Chamber of the Council of State, dated 09.02.2010 and numbered 2008/1143 E., 2010 1215 K. and the decision became final on 13.05.2010.
23. According to the construction contract in return for the land share signed between the parties, the delivery period of the construction is 17.10.2007 and the decision of the Antalya 2nd Administrative Court regarding the cancellation of the zoning plan was given on 05.04.2007. Upon notification of the said decision to Alanya Municipality, it is not possible for the municipality to issue a building occupancy permit for the construction on the plot that is the subject of the lawsuit.
24. The rope of the zoning plan

Since the decision regarding the subpoena is related to public order, it cannot be said that the contractor has been in default since it cannot be expected from him to continue the construction in violation of public order.
25. For this reason, the local court ruled that the zoning plan for the area where the construction is located was canceled before the contractor’s completion period expires and the municipality had to implement the decision of the Administrative Court, and the defendant was not at fault because the zoning plan for the area where the construction was located was cancelled. The decision to resist is right.
26. During the negotiations held at the General Assembly of Law, it was stated that the cancellation of the zoning plan could be considered as force majeure for the plaintiff, but it was necessary to determine whether the defendant had defaulted before the force majeure, although the Administrative Court canceled the zoning plan at the location of the immovable in question. Although it has been argued that the previous construction permit will not affect the validity of the construction permit, the cancellation of the zoning plan after the issuance of the construction permit will not prevent the right acquired by the landowners, and therefore it is not appropriate to give a decision of resistance by the court, while the decision of the Special Chamber should be complied with, but this opinion was not adopted by the majority of the Board for the reasons explained above. .
27. As such, the decision of resistance given by the local court is in accordance with the procedure and the law and must be approved.

IV. CONCLUSION:
For the reasons explained;
APPROVAL of the decision to resist with the rejection of the plaintiffs’ attorney’s appeals,
Since the required appeal fee is paid in advance, there is no need to charge any other fees,
In accordance with Article 440 of the Code of Civil Procedure No. 1086, which is being implemented in accordance with the Provisional Article 3 of the Code of Civil Procedure No. 6100, it was decided by a majority of votes on 06.10.2020, with the possibility of rectification open within fifteen days from the notification of the decision.

NEGATIVE VOTE

The decision to approve will have two shortcomings.
First, as of the delivery date, it will not be determined whether the zoning will be cancelled. However, if a research and investigation such as the Special Chamber’s reversal had been made, the issue would have been clarified.
Secondly, it is obligatory to obtain a building permit in order to build within the scope of the zoning plan. With the finalization of the zoning plan, right holders have the right to construct abstract structures. The right to construct an abstract building turns into a right to construct a concrete building upon obtaining a building permit. In the work titled General Principles of Building Law, (Taner Ayanoğlu Istanbul 2014), obtaining a building permit, its cancellation and its consequences have been examined together with the decision on administrative jurisdiction. The decision of the administrative court to cancel the zoning due to the deduction of the regulation partnership share (DOP) depending on the 18th article of the zoning law is a decision regarding the abstract construction right within the zoning plan. There is no decision taken by the administrative court regarding the cancellation of the construction permit, which has the right to concrete construction. The construction permit has a vested right dimension. The aspect of vested rights, such as respect for vested rights and not being affected by changing rules, has the appearance of necessity and appropriateness to expropriate if it will be affected. For a detailed discussion of the administrative jurisdiction on the subject, ibid. s. See 195 et al.
Mecelle 22 brought the general principle of “appreciation according to the amount of necessity”. Although the zoning ordinance has an imperative character regarding public order, I am of the opinion that there is a disposition that exceeds its purpose in the act of administrative jurisdiction. I think that a transcendent evaluation error was made when an administrative court decision regarding the annulment of zoning was accepted as if there was an annulment of the construction license and the conclusion was reached. If there was a decision to cancel the building permit, I would not have any objection to the result reached.
I cannot agree with the majority opinion regarding the affirmation of the decision to resist, for the two reasons I have briefly explained above. I am of the opinion that the decision to resist will be overturned, as in the decision of the Special Chamber to overturn it.

You can reach our other articles, sample decisions and petitions by clicking here.