General Assembly of Law 2020/168 E. , 2020/394 K.
“text of jurisprudence”
COURT : Court of First Instance
1. At the end of the trial held due to the “receivable” case between the parties, Istanbul Anadolu Dec. 28. Upon the appeal of the decision regarding the rejection of the case given by the Civil Court of First Instance by the plaintiff’s attorney, the Supreme Court of Cassation 15. The examination conducted by the Civil Chamber was eventually overturned, and the Court resisted the decision to disrupt the Private Apartment.
2. The decision to resist was appealed by the plaintiff’s attorney.
3. After examining the documents in the file by the General Assembly of Law, the necessity was discussed:
I. THE JUDGING PROCESS
Claimant Prompt:
4. In his Dec Decease dated Dec 05.02.2016, the plaintiff’s attorney stated that a construction and sale promise agreement was signed between his client and the defendants’ murisi Izzet Önel on Dec 06.09.1995 for the land share, that his client completed the construction in 1997 and delivered the apartments, and then a dispute arose between them in 2009, in a lawsuit filed by the landowner on the grounds that the building is contrary to construction, Istanbul Anadolu 15. 2009/343 of the Civil Court of First Instance. termination of the contract with the client file numbered with the shares on behalf of the decision on cancellation of the decision that has been made and confirmed by the Supreme Court, between the land owner of the land subject of the case with his client if it has 1/2 percent share separately, 4 apartments and 1 store owner and the client that is used by the client due to the cancellation of the shares on behalf of the land owner as the owner of the entire building, due to the effective termination of the contract, unjust enrichment, arguing that these should be disposed of according to the provisions of the legal relationship between, without prejudice to the rights regarding the surplus, he requested and sued that a decision be made to collect TL 10,000 from the defendants together with the interest to be processed from the date of 25.03.1997, when the building was delivered.
Respondent Response:
5. On the petition dated 02.03.2016 deputy defendants; that should have dismissed the case because of the statute of limitations, the case is building on the subject land prior Muris of their clients, subject of the case of the building of the building demolished by the client in return for a share of the plot on a lawsuit to demand the termination of the construction contract Istanbul Anadolu 15. 2009/343 of the Civil Court of First Instance. he defended the rejection of the case by stating that the termination of the contract with his numbered file and the cancellation of the land share on behalf of the defendant was decided, the decision was finalized by passing the Supreme Court audit, the building built by the plaintiff was made contrary to Deconstruction, the plaintiff was trying to collect the cost of construction that has no value.
The Decision Of The Court Of First Instance:
6. Istanbul Anatolia 28. The decision of the Civil Court of First Instance dated 21.06.2016 and dated 2016/52 E., 2016/185 K. with the decision numbered; Istanbul Anadolu 15. 2009/343 of the Civil Court of First Instance. and 2013/553 K. numbered in the file, where compensation is made on an unlicensed basis for the construction of the illegal nature of construction, zoning staying on the road in the implementation plan, the license would not be able to connect to the decision becomes final on the date 26.02.2015 determined and, according to the Supreme Court practice, illegal, and according to the zoning plan, the reconstruction of the building remaining fixed on the road that are in violation of the license has an economic value and economic value because they are not able to connect to non-compensation would not be required for the building, on the grounds that the case is dismissed.
The Decision to Spoil the Private Apartment:
7. Istanbul Anatolia 28. The plaintiff filed an appeal request against the above-mentioned decision of the Civil Court of First Instance by his attorney within the time limit.
8. Supreme Court 15. The Legal Department dated 29.05.2018 and issued 2018/927 E., 2018/2226 K. with the numbered decision;
Provisional 16 added to the Zoning Law No. 3194. 31.12.2017 made before the date of item that will be applied to the reconstruction of the content contrary to illegal structures and backward as it is an arrangement that has been planned to be implemented effectively, effective legal regulation of the procedure due to the vested right back with the exception of the aforementioned provision of the new regulations as applied to the case at hand the courts of Appeal as the Supreme Court, should also be considered that, accordingly, when the concrete case is evaluated, 16 of the Law No. 7143, which entered into force on 18.05.2018, on the Restructuring of Tax and Certain Other Receivables and Amendments to Certain Laws. provisional 16, which was added to the Zoning Law No. 3194 with Article. under Article should be investigated and could not be brought into legal structures are made of the fact that in this case, contrary to the reconstruction and construction of illegal structures for the implementation of urban transformation based on rewriting or record documents up to the structure even if only temporarily valid to the extent that enables them to be made legal, while in the aforementioned arrangement and apply the required processes are completed and the building is determined by obtaining the certificate of registration of the legal structure not made, the dispute should be reconsidered by the court stating that the decision by the corruption of, according to the reason for the annulment, it has been decided that there is no room for the other appeals of the plaintiff’s attorney to be examined for now.
The Decision to Resist:
9. Istanbul Anatolia 28. The decision of the Civil Court of First Instance dated 05.09.2019 and dated 2019/177 E., 2019/274 K. with the decision numbered; 16 of the Law numbered 7143, which entered into force alongside the previous grounds. provisional 16, which was added to the Zoning Law No. 3194 with its article. pursuant to Article 31.12.2017 construction for the reconstruction of the record made before the date of the construction of illegal structures and contrary to the implementation of urban transformation based on documents valid or recognized even if only temporarily up to the possibility of legalization, although the subject of the case the development plan of staying on the road for public building, structure, the granting of the certificate of registration of the document is not possible illegal construction and real estate development contrary to the registration as you get off of its path through the implementation of the zoning plan doesn converted to collapse by for every moment and is able to, even if the zoning plan is not implemented, the decision to resist was made on the grounds that the building should be demolished until the reconstruction and urban transformation is implemented at the latest, and the plaintiff cannot enrich himself due to the building.
Appeal of the Decision to Resist:
10. The decision to resist was appealed by the plaintiff’s attorney during the period.
II. DISPUTE
11. 16 of Law No. 7143 by the court in relation to the structure, which is uncontested to be contrary to construction and illegal in the concrete case. provisional 16, which was added to the Zoning Law No. 3194 with its article. in accordance with the article, it is collected at the point of whether it is necessary to investigate whether the building has been made legal by obtaining a building registration certificate.
III. reason
12. In terms of resolving the dispute, firstly, the provisional 16, which was added to the Zoning Law No. 3194 with the Law No. 7143. in the case of obtaining a building registration certificate in accordance with the article, it was useful to make general explanations about the status provided by this document.
13. The Law No. 7143 and the Zoning Law No. 3194 are temporary 16. item added in the first paragraph of the article and disaster risk preparedness and its annexes within the scope of unlicensed or license in violation of registration and reconstruction of structures in order to achieve peace, 31.12.2017 made before the date of the institution and the authority of the Ministry of Environment and urbanization for structures and organizations 31.10.2018 be applied until the date of this article, until the date of payment of the registration fee and the fulfillment of the terms in the certificate of registration issued on 31.12.2018 where arrangements can be included.
14. The expression ”building registration document” was first added to our law in the Zoning Law No. 3194, provisional 16. he entered with substance. Provisional 16 added to the Zoning Law No. 3194. the motive of the item “in their preparation for Disaster Risk unlicensed, and in violation of its license or registering with the Annexes of the structure in violation of the zoning regulations by providing finance to projects of conversion, the transformation will be done faster and more efficiently in order to 31.12.2007 made before the date of structures, building owners and their recording system according to the declaration upon application to the processing of these structures to be prepared for the structure of water, electricity and natural gas to be able to connect to the judiciary and the decisions taken in order to reduce the workload and fines collected in municipalities that are not sacrificing demolition, if the consent of half of the owners is found, a change of breed and condominium ownership can be established without seeking a building use permit, ”it is stated.
15. When the mentioned article is evaluated together with the justification as a whole, it is understood that by submitting this document on structures contrary to construction as a result of the application, an authorization is given to the owners related to the use of the structure, an administrative status is provided for the use and possession of the structure. This status, which is provided by issuing a building registration certificate, provides protection to the building owner by the administration regarding the use of a building that is not protected due to its violation of the zoning legislation and actually needs to be demolished.
16. Provisional 16/3 of the Zoning Law No. 3194. in the article, it is clearly stated that the building registration document is intended for the purpose of use of the building. Considering these issues, it is understood that the regulation allows the use of structures that are contrary to construction and should be demolished, and the administration allows the building owner to use the structure.
17. In addition, in the provisional Article 16/10 of the Zoning Law No. 3194, it is clearly stated that the building registration certificate is valid until the reconstruction of the building or the implementation of urban transformation, and the provisions of the zoning legislation in force will be applied in the case of renovation of the buildings for which the building registration certificate is issued. This provision is understood in particular that the building registration document provides a temporary status for the use of the building, the building is allowed to be used by the administration despite the fact that it is contrary to zoning with this status, but it provides for the implementation of the provisions of the zoning legislation in force in the event of renovation of the building.
18. Provisional 16/1 of the Zoning Law No. 3194. in case of moving the conditions specified in the article, the immovable property owner is granted the right to obtain a building registration certificate, and there is no mandatory statement for the immovable property owner to use this right here. Taking this situation into account, no one will be forced to apply for a building registration certificate without their consent. In the construction contract for a land share containing mutual actions, the contractor will not be able to force the land owner to obtain a building registration certificate for the building he has built in violation of Deconstruction Deconstruction.
19. When the real estate owner receives a building registration certificate related to the building that is contrary to the construction, it will be possible to use the building, but the building registration certificate will not make the building suitable for zoning in order to be resettled, as stated above.
20. When the concrete event is evaluated in the light of these principles and explanations; the construction contract signed between the plaintiff and the defendants’ muri for the land share, Istanbul Anadolu 15. Dec. Dec. It is understood that with the decision of the Civil Court of First Instance dated 06.11.2013 and numbered 2009/343 Basis, 2013/553 Decision, the structure built by the plaintiff was built contrary to the construction and its termination was decided due to the impossibility of obtaining a housing license.
21. Provisional 16, which was added to the Zoning Law No. 3194 with the Law No. 7143. when the regulations contained in the article are taken into account, the building registration certificate is related to the use of the building contrary to the construction and does not make the building suitable for construction. The building registration certificate is valid until the reconstruction of the building or the urban transformation application and provides a temporary status for the use of the building. In this case, it will not be effective to determine whether the defendant real estate owners have received the building registration document.
22. For the reasons explained, the decision to resist that there is no need to investigate whether the defendant real estate owners have applied to the administration to obtain a building registration certificate is in place.
23. However, since the appeals on the merits of the case are not examined by the Special Chamber, the file should be sent to the Special Chamber for the examination of the appeals on these aspects.
IV. result:
For the reasons explained;
The decision to resist is in place and 15 of the file for the examination of appeals on the merits of the case. TO BE SENT TO THE LEGAL DEPARTMENT,
However, due to the fact that the decision correction path is open, first of all, the court must fulfill these procedures, if the decision correction path is applied, the file will be sent to the General Assembly of Civil Law, and if not, the court will send it directly to the Special Office,
Provisional 3 of the Code of Civil Procedure No. 6100. 440 of the Code of Civil Procedure No. 1086, which is applied in accordance with Article. in accordance with the article, a unanimous decision was made on 10.06.2020, so that the way to correct the decision is open within fifteen days from the notification of the decision.