General Assembly of Law 2017/503 E. , 2017/1190 K.
“text of jurisprudence”
COURT : Commercial Court
At the end of the trial due to the original, united and reciprocal “receivable” case between the parties; Kadıköy 3. Dec. The Commercial Court of First Instance of the main case 1.735.262,82 TL. 27.12.2011 days and 2005/421 E given regarding the acceptance of the counterclaim, the rejection of the counterclaim, and the recognition of the merged case, which is not followed by the parties, as unopened.-2011/882 K. upon the request of the numbered decision by the defendant-counter plaintiff cooperative attorney, the Court of Cassation 15. The date of the Law Office is 16.01.2014 and 2013/4701 E. 2014/354 K. with the numbered decision;
“…The main case is the determination of the injustice of the termination made by the defendant business owner cooperative and the decision to collect the balance of the work price; the counterclaim is related to the collection and compensation of the cost of incomplete and defective work with the excess payment paid to the contractor company, and the joint case filed by the contractor company is related to the collection of the cost of excess work performed out of the contract. The court’s decision on the acceptance of the original case, taking into account the amount increased by the reform, the rejection of the counterclaim, the decision that there is no room for establishing a judgment on the merits of the merged case was appealed by the defendant and the counterclaim business owner cooperative.
October 1994 is an additional agreement between the parties to the “Housing Construction Contract” dated 02.02.1994 and the “Housing construction contract dated 02.02.1994″ dated 12.07.1997. Dec. contracts made in ordinary written form titled “have been arranged; these contracts are 355 of the Law of Obligations No. 818. the work defined in the provision of the article is in the nature of a contract.
In the original case, the plaintiff contractor company stated that it had fulfilled its performance in accordance with the original and additional contract provisions, and that the defendant cooperative had terminated the contract unfairly after completing the construction subject to the contract by 95%, and requested October to decide on the collection of the balance work price by determining the unfairness and invalidity of the termination. In order for the contractor to be entitled to the cost of the work, he must perform the construction in accordance with the contract, plan and project, zoning legislation and technical rules and deliver it to the owner of the work. In the concrete case; in the expert report dated 02.06.2008 received by the court, “architectural, static, installation, heating and thermal insulation projects certified by the municipality of the constructions subject to the case and the buildings subject to the case are in the state of illegal construction, as there is no construction permit approved by the municipality again”. 21 Of the Zoning Law No. 3194. in accordance with Article 26. with the exception of the exceptions listed in the article, it is mandatory to obtain a building license for all buildings. The conditions required for the issuance of a license are 22 of the Zoning Law. it is shown in the article. On the contrary, if there is no provision in the contract, the obligation to obtain a license belongs to the business owner. October 30 of the Zoning Law No. 3194, since it is not decided that the Decisionof obtaining a building permit belongs to the contractor in both the original and additional agreements between the parties. in accordance with the provision of the article, the act of obtaining a building permit belongs to the cooperative that owns the business. Constructions that are not carried out in accordance with the license obtained without obtaining a license or even if a license is obtained are defined as “illegal construction”. According to the established practice and case law of our Department, the building that is made contrary to the provisions of the Zoning Law No. 3194, which contains mandatory legal rules, does not express economic value unless it is made legal because it is a “illegal building”. Since it does not have economic value, the contractor cannot ask for the cost of work and production of this nature. However, if the work is brought to a legal status, the contractor may claim the work price he deserves.
In these circumstances, the first defendant are within the scope of the owner of the business since the Cooperatives Act of making and building permits can be obtained so that the legal construction business owner sufficient time and authorizing the cooperative; the cooperative’s get building permits and construction in the case of making it legal for the same reason, the contractor company and the appropriate authorization to be given time to be given to the appropriate authority and are not regulated despite the time when that wouldn’t be talking about the economic value of the construction, the contractor filed by the decision of the denial of the original trial must be given.
If the constructions are made legal; Üsküdar Chief Public Prosecutor’s Office’s indictment dated 11.09.2006 from the scope of the file Üsküdar 2 on embezzlement and abuse of office against many defendants, including contractor company officials and cooperative officials. It is understood that a public lawsuit has been filed in the file of the Assize Court registered under the main number 2006/272 and that this case is still pending. Article 53 of the Code of Obligations No. 818. in accordance with the Article, material facts that are subordinate in criminal proceedings bind a civil judge. In other words, it is clear that the material cases that subuta in the criminal case will be taken into consideration in the civil case. The finalized determination of the criminal court regarding the determination of the event subject to dispute, in other words, the existence of the event and the material facts related to its commission by the defendant, also constitutes a final judgment in the civil court on the same issue. Then, since the results of the current criminal case will affect the civil case subject to appeal, the court expects the outcome of the case, which is being tried at the Üsküdar High Criminal Court, after the decision on the criminal case is finalized, the material facts and all the evidence collected in the criminal case will be evaluated and the expert expert panel of 3 people who will be assigned to reveal the truth will be reconnoitered on the spot with the expert expert panel, a report that is suitable for audit and justified should be received and the amount of the work cost that the contractor deserves should be determined within the framework of the result that will occur.
Without focusing on the issues described, the provision of the judgment in writing with incomplete examination was not correct, the decision had to be overturned … ”
istanbul Anadolu 4. At the end of the trial, which was disrupted on grounds and turned back to the file instead of the file (the file was transferred to him). The Commercial Court of First Instance resisted the previous decision.
DECISION OF THE GENERAL ASSEMBLY OF LAW
By examining the law at the time of decision has been appealed by the General Assembly to resist it been understood that this law should be applied from the date of the decision of 1086 438 of the second paragraph of the provision in accordance with attorneys to appeal the decision and request a hearing on the lawsuit the plaintiff who do not noble, it shall be dismissed and the combined file after you have discussed the need to read the papers was:
The cases combined with the original and counterclaim are related to the claims for the collection of receivables arising from the work contract.
The plaintiff’s attorney with his client according to the agreements concluded between the original and the additional defendant, the defendant belonging to deliver by doing construction on a plot of the number of independent sections that would start to be used said, but part of the price paid by the defendant whether the defendant has been made by yanc setting forth the determination of invalidity and termination of injustice, the balance of the price of merit 1.744.650,73 TL receivables, without prejudice to the rights of the surplus and the demand on the case for now 60.000,-TL rediscount interest you commit to the process and the decision to buy the collection with demand and has prosecuted.
In the merged case, the receivable related to the additional works performed (at the October date of the case in hand) has been the subject of litigation.
The plaintiff’s attorney increased the case value to TL 1,735,262.82 with the correction dated 28.10.2010.
The defendant’s attorney stated that the plaintiff could not complete the construction in the time he had committed, that the building was not in compliance with the General Specifications of Public Works, that additional costs should be incurred to eliminate this problem; the plaintiff’s failure to fulfill the responsibilities of the cooperative tax and other legal due to the financial burden that was brought, the defendant, through processing between the managers of the cooperative with the authorities of the former client, actually 1.300.000,-TL has already been issued and paid more if you have found that around the previous administration, also has started criminal proceedings against those concerned, if at the end of the period of notice given to correct the deficiencies on the opposite side of that upon the termination of the contract upon failure to fulfill the act, the temporary and final acceptance and final accounts were not made to, stating that the use of independent sections would not mean surrender, he asked for a decision to dismiss the case;
In his counterclaim, he demanded and sued that the collection of the 10.000,-TL portion of the overpayment paid to the plaintiff around 1.300.000,-TL be decided for now.
The court, taking into account the productions made by the plaintiff and the defendant’s payments, paid the original case 1.735.262,82 TL. acceptance of the counterclaim, rejection of the counterclaim, and the combined case, which was not followed by the parties, was removed from the transaction (HMK.m.150), the decision that there is no place to establish a judgment on this case was overturned by the Special Chamber on the grounds shown above upon the appeal objection of the defendant-counter plaintiff’s attorney, and it was decided that there is no place to examine other appeals for now.
The court resisted the previous decision on the grounds that the plaintiff contractor has no obligation to obtain a license, that the plaintiff completed and delivered the work, thus fully performing his contractual performance is indisputable, and that the result of the criminal proceedings after this stage will not affect the case at hand.
The decision to resist was appealed by the defendant-counter plaintiff attorney.
The dispute that comes before the General Assembly of Civil Law by way of resistance; whether the contractor or the business owner has the obligation to connect the building to the license in accordance with the work contract in terms of the concrete event, whether it is possible to eliminate this deficiency and whether the price claim can be connected to it, and whether the criminal proceedings against the cooperative managers and the plaintiff company official have an impact on the file at hand.
The original and merged file plaintiff… Zoning Inş. Taah. Tic. Ltd. contractor, defendant and counter plaintiff …. Akören Housing Construction Cooperative is the owner of the land Dec. Dec Dec oct 12.07.1997 and original work contracts dated 02.02.1994 were made between the parties, with this the contractor undertook to build a building on the land for the cost. October 19, 1994.
The contract in which the contractor undertakes to create and deliver a work of art in exchange for a price paid by the owner of the work is called a “work contract” (Eren, F.: Special Provisions of the Law of Obligations, 2.b., Ankara 2015, p.584; Selimoglu, E.: Istisna -Eser- Convention, Ankara 2010, p.1).
As can be understood from the definition, the work contract is a contract that imposes a debt on both parties. The contractor’s principal obligation arising from the contract is to create a work and deliver it to the work owner (818 p. TALK.m.355; 6098 pp. TBK.m.470). The work that is created and delivered to the business owner must be “shameless”. The law has not given a clear definition of shame. However, he made a ranking about the weight of shame. According to the law, the work is “…defective to the extent that the business owner cannot use it or be forced to accept it in fairness” and “repair is possible if it does not require excessive costs” (818 p. TALK.m.360/I-II; 6098 p. TBK.m.475/1-3).
According to the definition adopted by weight in the teaching; It is accepted that the work is defective if the work created does not carry the qualities specified in the contract or if it lacks the qualities that should be present in the work according to the rule of honesty (Eren, p.634; Turanboy, A.: According to the Decisions of the Supreme Court, the Contractor’s Liability Arising from Deficiencies and Defects in Construction After Delivery, AÜHFD., C.XLI (1989-1990), P.1-4, s.157 et seq.; Canpolat, F.: The Rights of the Business Owner Arising from the Monopoly Against Defect in the Exception Agreement, Ankara 2009, p.65).
Both in teaching and in practice, shame is classified as material, legal, economic and aesthetic shame. It is useful to focus on “legal shame” in this classification. Legal shame is the existence of limits on the subject of performance that prevent the buyer from benefiting from it or saving on it, affect the value of the property or the expected benefit from it, and generally arise from public law (Aral, F./Ayranci, H.: Law of Obligations Private Debt Relations, 10.b., Ankara 2014, p.119; Coffeemaker, N.: Return of the Consumer from the Contract Due to Defective Goods in the Sale of Movable Property, Ankara 2014, p.9).
As a matter of fact, in accordance with Article 21 of the Zoning Law No. 3194, it is necessary to obtain a building (construction) license for all structures that fall under the scope of this Law. According to Article 22 of the law, building owners or their legal deputies must apply to the municipal or governor’s offices with a petition to obtain a building permit; only the title deed (a document that will replace the deed deed in exceptional cases), architectural project, static project, electrical and installation projects, pictures and accounts, a sketch with a reference or, if not, a size must be added to the petition. If the building is unlicensed or built in violation of the license and October and cannot be made in accordance with the license, the building must be demolished (Zoning K.m.32). In addition, administrative sanctions related to unlicensed buildings are also applied (m.42).
It should be noted immediately that the provisions of the Zoning Law are related to public order and are monitored ex officio by the courts and the Supreme Court.
From the evaluation of the Decency provisions in the work and the articles of the Zoning Law together, it is concluded that even if an unlicensed building is complete in a physical (material) sense, it will be considered legally defective and the contractor’s liability arising from the defect can be considered.
On the other hand, in the face of the contractor’s obligation to create and deliver the work, the act imposed by the work contract on the work owner is to “pay the price” (818 p. TALK.m.355; 6098 pp. TBK.m.470).
Unless there is a right to performance later according to the terms or characteristics of the contract, in contracts containing mutual acts, the party requesting the performance of the contract must first have performed its own debt or proposed its performance (818 p. TALK.m.81; 6098 pp. TBK.m.97). In the work contract, it is also subject to the condition that the contractor requests payment of the price, delivers the work without shame, or declares that he is ready to pay. The business owner cannot be forced to take delivery of the defective work; in this case, the business owner’s debt to pay the price will not be incurred. The owner of the business can avoid paying until the shame is removed (Baygın, C.: According to Turkish Law, the Fee and the Provisions to which it is Subject in the Exception Agreement, Istanbul 1999, p.193-194).
In terms of work contracts, the subject of which is construction (building construction), it is necessary that the building complies with the contracts and annexes, science and art pedestals, certified project, license and other zoning regulations; otherwise, it is concluded that the work is defective, and in this case the contractor cannot qualify for the cost of work October.
Unless otherwise agreed in the contract, the obligation to obtain a building permit belongs to the owner of the business (land); the fulfillment of this Decency cannot be expected from the contractor. However, a competent contractor who bears the title of a prudent businessman should not start construction and continue it without a license and a project. If the contractor has acted contrary to this principle, in other words, if he has completed the building without obtaining a license and the necessary permits, he cannot be entitled to the cost of the work. In such a case, the contractor’s right to the cost of the work depends on the elimination of project and license deficiencies, if possible. In the same way, the business owner cannot request the expense of the existing deficiencies and defective works in a construction that does not have a project and license.
Looking at the concrete case;
Üsküdar Municipality Zoning department response letter indicated the absence of a project to the subject matter of the case is immovable; this type of move in the same volume 30.09.2014 day and whose subdivisions are 6215-6311 the absence of a complete reconstruction, therefore, any holiday was held about the construction of the memorandum of many construction and zoning application where efficiency have been reported. Üsküdar, which is in the file again, is 5. 2004/55 D of the Civil Court of First Instance. Business identified in the expert report dated 19.10.2004 to a numbered file with the opinion held by bilirkisilerce 02.06.2008 prepared in the case referenced in the blog, the report also involved in the case by the municipality approved the construction of architectural, structural, plumbing, heating and thermal insulation project, the absence of” an unlicensed and situation of the building in the case of “illegal construction” it is stated in nature that are. The contractor also has no claim to have a project and building permit (construction permit).
When the principles described above and the concrete event are evaluated together, it is indisputable that the contractor cannot request a work fee due to construction that is not Decommissioned in principle. However, in a recent application of the Supreme Court, because of that, the decision of the case, considering that lead to the victimization of the denial of the contractor, the court approved the project for construction without a building permit and primarily to bring them into line with the zoning regulations from the relevant authorities, it is possible to be asked, with additional reports from experts that can be and should detect; after this research and examination, it is understood that it will not be possible to connect the building to the project and license in any way, considering that the economic value of the building that should be demolished in such a case is also absent, it has been adopted that the case regarding the manufacturing cost filed by the contractor should be dismissed. It is determined that the legalization of the building is possible (in case the obligation to obtain a building permit belongs to the business owner as) primarily business owner and a construction should be given the necessary time to prepare projects baglatmas license, but it’s being able to supply this requirement if the contractor fails to comply with the building if it is made legal and the contractor should be given to the fabrication of otherwise ask for the price it should be considered whether you could ask for.
As for the decision to disrupt and resist the decision to make the file on the criminal trial a pending matter in the event that the constructions are legalized in terms of the counterclaim;
At this point, first of all, it is worth focusing on the impact of criminal court decisions on the civil case, in other words, which decisions of the criminal court will bind the civil courts:
The effect of the decisions of the criminal court on the civil court (case), in our jurisprudence 6098 p. Article 74 of the Turkish Code of Obligations (818 p. TALK.m.53) has been regulated and the civil judge has been made independent in principle in the face of the finalized decisions of the criminal court. This principle is based on the principle that criminal rules sanction a ban in terms of public interest, while the rules of law that cover the same dispute regulate personal relations in the field of civil law and, in particular, stipulate compensation conditions.
6098 pp. Article 74 of the Turkish Code of Obligations regulating the subject:
“When the judge decides whether the perpetrator has a fault or not, whether he has the power to distinguish, he is not bound by the provisions of criminal law related to responsibility, nor is he bound by the acquittal decision issued by the criminal judge.
In the same way, the decision of the criminal judge on the assessment of the defect and the determination of the damage does not bind the civil judge ”.
In the face of this clear judgment, there is no hesitation that principles such as the acquittal decision given by the criminal court, the degree and degree of defect, the amount of damage, the power of appeal and the adequacy of the imposition, and the necessity will not bind the civil judge.
It should be noted right away that this independence of the civil judge, described above, is not unlimited. Both in the teaching and in the established case law of the Court of Cassation, it is accepted that the civil judge will be completely connected with the material events determined by the criminal judge, and in particular with the issue of “unlawfulness of the act”. In other words, the decision of the criminal court, which determines the material events and the existence of prohibited acts, is conclusive evidence on the part of the parties (HGK., 10.01.1975 day and 1971/T-406 E., 1975/1 K.; 23.01.1985 days and 1983/10-372 E, 1985/21 K; 27.04.2011 days and 2011/17-50 E, 2011/231 K; day of 03.04.2013 and decisions No. 2012/19-873 E, 2013/433 K).
Civil trial is a procedural form of law. The opening of the case, the putting forward of objections, the notification of witnesses and other evidence are subject to certain time conditions, as well as certain restrictions have been imposed for the purpose of quickly concluding the trial, such as the inability to provide a second witness list, the prohibition of expanding the claim and defense. As a result of this, the form of the judge of law will seek the truth, the material truth will not be the primary goal. However, the criminal judge, on the contrary, will try to reach the material truth as the primary goal. Therefore, Article 74 of the Turkish Code of Obligations does not constitute an obstacle to the binding of a civil judge by the finalized decision of the criminal court determining the link of material causality (illity) (Çenberci, M.: Final Judgment in Civil Cases, Ankara 1965, p.22 et seq.; also HGK., 16.09.1981 day 1979/1-131 E., 1981/587 K.; 27.04.2011 day and decisions No. 2011/17-50 E, 2011/231 K; 03.04.2013 day and 2012/19-873 E, 2013/433 K).
According to the established practice of the Court of Cassation and the general acceptance in the doctrine, the decision of the criminal court on the determination of the material fact binds the civil judge. Despite the finalized acceptance of the existence or absence of a material event in a criminal court, it is not possible to re-discuss the same issue in a civil court.
When the concrete situation is evaluated in the light of all these explanations;
Üsküdar 2. (now Istanbul Anadolu 6.) of the High Criminal Court (before overturning) 2006/272 E. the decision made at the end of the case filed on the charge of “embezzlement and abuse of office” in the file registered with the number is 5 of the Supreme Court. Day of the Criminal Department 04.12.2012 and 2010/9570 E., 2012/12454 K. with the numbered decision, some of the defendants, including the defendant cooperative managers and the plaintiff company officials, have been corrupted for the investigation of the defendants. It is understood that the case referred to in this form is still the most urgent. It is indisputable that the decision made in the trial to be held after the annulment will affect the receivable case at hand. In this case, waiting for the outcome of the case, which is being tried in the High Criminal Court, after the decision to be made in the criminal case is finalized, the material facts that subtract from the criminal case and all the evidence collected will also be evaluated and the fact will be assigned to reveal the expert 3-person expert panel to conduct an on-site discovery, October October Dec. by obtaining an audit-friendly and reasoned report, and thereby eliminating the main and additional reports and the contradictions between the additional reports themselves (HMK.m.281) within the framework of the result to be formed, it is necessary to determine the amount of the work price that the contractor deserves.
Finally; the merged case is considered to be unopened (HMK.m.150) although the decision was made “… 1.500, which was appreciated for the defendant’s attorney,-TL. the provision established in the form of ”The power of attorney fee is taken from the defendant and given to the plaintiff” is also contrary to Article 326/1 of the Code of Civil Procedure and required to be overturned.
According to the explanations made above, while the decision to disrupt the Private Apartment, which was also adopted by the General Assembly of Law, should be followed, resisting the previous decision is against the procedure and the law.
Therefore, the decision to resist must be overturned.
RESULT: Defendant-plaintiff’s counsel on appeal against the decision to resist the adoption of a private cooperative of Appeals decision in the circle of 1086 429 of Law pursuant to this article for additional reasons shown above CORRUPTION, upon request, in advance of provision for the correction of Appeal decision to open the back of tuition 14.06.2017 way she tucks on the day it was decided unanimously.