T.C.
JUDICIARY
GENERAL ASSEMBLY OF LAW
E. 2008/11-152
K. 2008/162
T. 27.2.2008
– ANNULMENT OF EVICTION UNDERTAKING ( THE CASE FILE RELATED TO THE EVICTION CASE SHOULD BE BROUGHT AND IT SHOULD BE EVALUATED WHETHER THE DECISION GIVEN IN THAT CASE WILL CONSTITUTE A FINAL JUDGMENT OR CONCLUSIVE EVIDENCE OR STRONG DISCRETIONARY EVIDENCE FOR THE CASE AT HAND )
– EVICTION CASE (THE RELATED CASE FILE SHOULD BE RETRIEVED AND IT SHOULD BE EVALUATED WHETHER THE DECISION GIVEN IN THAT CASE CONSTITUTES A FINAL JUDGMENT OR CONCLUSIVE EVIDENCE OR STRONG DISCRETIONARY EVIDENCE FOR THE CASE AT HAND – CANCELLATION OF THE EVICTION COMMITMENT)
– DECISION TO RESIST IN THE NATURE OF A NEW JUDGMENT ( THE DECISION SUBJECT TO APPEAL IS NOT A DECISION TO RESIST IN REALITY, BUT A NEW JUDGMENT FORMED BY TAKING INSPIRATION FROM THE REVERSAL AND MAKING AN EVALUATION IN LINE WITH THE REVERSAL ) 6762/M.336, 337

SUMMARY : Since the plaintiff’s attorney, who did not appeal the previous decision of the Local Court in the same direction, has no legal interest in appealing the decision of resistance, the appeal petition should be rejected. In the decision of reversal, in the face of the fact that the defendant Turkish Aeronautical Association’s attorney stated that an eviction case was filed by his client against the plaintiff tenant before the present case based on the eviction undertaking subject to the case at hand, and that the decision was finalized; it was pointed out that the case file related to the eviction case should be brought and it was necessary to evaluate whether the decision made in that case would constitute a final judgment or conclusive evidence or strong discretionary evidence in terms of the case at hand. In the reasoning of the decision of the Local Court subject to appeal, it is stated that the decision rendered in the eviction case will not constitute a final judgment for the case at hand, since the parties, subject matter and reasons of both cases are different. In this case, the decision subject to appeal is not a decision of resistance in reality; it is a new judgment inspired by the reversal and evaluated in line with the reversal. Therefore, the task of examining the judgment on appeal belongs to the Special Chamber, not the General Assembly of Civil Chambers.

CASE : At the end of the trial held due to the cancellation of the evacuation commitment and compensation lawsuit between the parties; Upon the request of the defendants’ attorneys for the examination of the decision dated 8.4.2004 and numbered 2003/900-2004/357 given by the 9th Commercial Court of First Instance of Istanbul regarding the acceptance of the lawsuit, with the decision of the 11th Civil Chamber of the Court of Cassation dated 24.5.2005 and numbered 2004/11105-2005/5480;

( … The plaintiff’s attorney, in the original and amalgamated lawsuit petitions, stated that the immovable property used under the name of M. Antique Hotel, owned by the defendant Turkish Aeronautical Association, was leased to his client company with a lease agreement dated 16.5.1985, but since a company to be a partner was needed for the repair of the abandoned and unusable building, the non-suiting company L. Laleli Otelcilik Yatırım Turizm ve Tic.A.Ş. was established, the client company also had shares in L. A.Ş., the hotel was transformed into a five-star hotel and opened for operation by making expenses, the defendant Çetin S. was elected as a sole shareholder in the extraordinary general assembly of the client company dated 07.06.2000. 2000, the defendant Çetin S. was authorized to represent and bind the company individually at the extraordinary general assembly of the client company dated 07.06.2000, the said defendant signed the evacuation commitment dated 27.11.2000 and transferred his shares in the company on 01.12.2000. 2000, and stated in the transfer agreement that he did not conceal anything in the company records and that he did not make any commitment, that the survival of his client company depends on the continuation of its rights in the hotel, that a general and board of directors decision must be taken on such an important issue, and that the eviction commitment given with the signature of the shareholder who is the sole representative in this matter is invalid, and that giving an eviction commitment is not one of the duties of the company representative, the power of representation granted to the defendant is for ordinary daily transactions, since the lease agreement was signed by four decisions on behalf of the plaintiff company, at least the signatures of those who signed the lease agreement should also be included in the eviction commitment, after the defendant THK notified L. A.Ş., which was the actual tenant in the immovable, that the lease period was extended from 2000 until 2020 with the letter sent by the defendant THK, based on the eviction commitment dated 27.11.2000, the malicious partner Çetin S. ‘s actions by participating in facilitating the actions of the malicious partner Çetin S., claiming that the shareholders of the client plaintiff company changed completely on 01.12.2000 with the transfer of shares, and that no one who was aware of the eviction commitment dated 27.11.2000, four days before the former partner transferred his shares, would take over the shares, and arguing that 27. 11.11.2000 dated evacuation undertaking, and demanded and sued to be decided to collect (20.000.000.000) TL (20.000.000.000) from the defendant Çetin S. within the scope of articles 336-337 of the TCC, together with interest, and waived the claim for compensation.

The defendant Çetin S.’s attorney stated that his client had personal liability in the lease agreement, that one of the conditions put forward by his client in the negotiations before the share transfer was to give a future eviction commitment in order to prevent the liability arising from the lease agreement, that the share transfer price was kept low for this reason, that his client was authorized to represent and bind the company in the broadest sense in all matters, and requested the dismissal of the lawsuit.

The defendant Turkish Aeronautical Association’s attorney stated that his client cannot be directed against, that in the eviction case filed in Ankara 7 Civil Court of Peace due to the eviction commitment, all the claims put forward in the lawsuit petition came to the agenda, were rejected by the court and it was decided to evacuate the immovable, and requested the dismissal of the lawsuit.

The Court, based on the allegations, defense and the evidence in the file, L. Laleli Otelcilik Yatırım ve Turizm A.Ş. was established for the implementation of Article 12 of the lease agreement between the parties, all rental fees paid to the defendant THK were paid by L. A.Ş. and THK had no objection to this, in the determination made in the file numbered 1993/108 D.İş, it was determined that the leased place was being operated by L. A.Ş. and that the touristic operation certificate was in the name of L. A.Ş. A.Ş., that the touristic operation certificate was in the name of L. A.Ş., that the THK responded to the application made by L. A.Ş. for the revision of the lease conditions without objecting to the tenancy of L. A.Ş., by putting forward different conditions, and that before the eviction commitment subject to the lawsuit, on 15. 5.2003 before the eviction commitment subject to the lawsuit, L. A.Ş. paid the 6-month rent to the THK, there was no objection to this payment, moreover, L. A.Ş. was in charge of the payments throughout the contract, the eviction commitment given by Çetin S. on behalf of the plaintiff company was not connected with L. A.Ş. and would not bind it, although the actual tenant was L. A.Ş., Çetin S. A.Ş., it was decided to cancel the eviction commitment dated 27.11.2000 and to reject the compensation claim due to waiver, on the grounds that the lawsuit filed against this defendant should be accepted since the defendant THK obtained an eviction decision from the Civil Court of Peace based on the commitment given by Çetin S.

The decision was appealed separately by the attorneys of the defendants.

The dispute between the parties relates to the request for the cancellation of the commitment given by Çetin S., the former representative of the plaintiff company, on behalf of the plaintiff, regarding the eviction of the plaintiff from the immovable property where the company is a tenant.

Since it is defended by the defendant Turkish Aeronautical Association that before the filing of this case subject to appeal, the defendant lessor Turkish Aeronautical Association filed an eviction lawsuit against the plaintiff company based on the eviction commitment subject to the lawsuit, as a result of the trial, the eviction was decided and the aforementioned decision became final, the case file of the Ankara 7th Civil Court of Peace No. 2003/549 Esas, 2004/150 K. The case file numbered 2003/549 Main, 2004/150 K. of the Ankara 7th Civil Court of Peace regarding the eviction case should be brought into this case file and a decision should be made within the framework of the result that will be obtained by evaluating whether the decision made in line with the claim and defense put forward in that file will constitute a final judgment or conclusive evidence or strong discretionary evidence in terms of this case file subject to appeal, while it is necessary to make a decision within the framework of the result that will be obtained, it has been erroneous to establish a written judgment with incomplete examination without making an evaluation on this issue and it has been necessary to decide to overturn the decision in favor of the defendants for the explained reason… ),

The case was reversed and the file was returned to its place, and at the end of the retrial, the court resisted the previous decision.

The decision of the General Assembly of Civil Chambers was examined and after it was understood that the appeal was filed in due time and the papers in the file were read, the necessity was discussed:

DECISION : The main lawsuit and the consolidated lawsuit are related to the request for the cancellation of the eviction undertaking given by Çetin S., the defendant of the main lawsuit, to the Turkish Air Association, the defendant of the consolidated lawsuit, on behalf of the company, which is the plaintiff of both lawsuits.

The attorney of the plaintiff G. Denizcilik Ticaret A.Ş., in both the original and the consolidated lawsuit, stated that the defendant Çetin S., who has been a shareholder of the plaintiff company since its establishment, has given an eviction commitment letter dated 27.11.2000 to the other defendant, who is the lessor, without authorization and by concealing it from the company, in violation of the rules of good faith. 2000 dated evacuation undertaking, and shortly afterwards he transferred his shares and left the partnership; and demanded and sued for the annulment of the legally invalid evacuation undertaking and for the collection of 10.000.000.000 TL financial compensation from the defendant Çetin S.; during the trial, he postponed his claim for compensation with a petition dated 29.3.2004 and repeated this statement in the session held on 8.4.2004.

The attorneys of both defendants requested the dismissal of the lawsuit; the attorney of the defendant Turkish Aeronautical Association stated that an eviction lawsuit was filed by his client based on the commitment letter subject to the lawsuit and that it resulted in acceptance and that the decision was finalized.

Local Court; ( … The defendant Çetin S., who gave the letter of undertaking subject to the lawsuit, was authorized to represent and bind the plaintiff company in the broadest sense with the circular dated 27.11.2000, and gave the letter of undertaking based on this authority. As a result of the lawsuit filed based on the eviction undertaking, it is understood that the Ankara 7th Civil Court of Peace ruled for the eviction of the immovable property and the decision has not been finalized. The defendant Çetin Saraç transferred his share in the company with the share transfer agreement on 1.12.2000, after he gave the commitment letter. Although the plaintiff company appears as the tenant in the lease agreement, according to the scope of the file, it is understood that the tenancy of L. A.Ş. was accepted by the defendant Turkish Aeronautical Association, the defendant Çetin Saraç gave the eviction undertaking on behalf of the plaintiff company and this eviction undertaking is not related to L. A.Ş., which actually uses the immovable, the tenancy title actually and legally belongs to L. A.Ş., and the eviction undertaking does not bind the tenant. The defendant Çetin S. caused an eviction decision to be taken against the plaintiff company by giving the eviction commitment letter, thus causing damage. The defendant THK., on the other hand, although L. A.Ş. is actually a tenant in the immovable property, based on the commitment letter, by abusing its authority with Çetin S., it has taken an eviction decision to the detriment of the plaintiff company… ), decided to accept the lawsuit, to cancel the eviction commitment letter dated 27.11.2000, and to reject the compensation claim due to waiver; upon the appeal of the attorneys of the defendants, the judgment was reversed by the Special Chamber with the above-mentioned decision; the Local Court decided to resist and this decision was appealed by the attorneys of the parties.

1- Since the plaintiff’s attorney, who did not appeal the previous decision of the Local Court in the same direction, has no legal interest in appealing the decision of the Local Court, his appeal petition should be rejected.

2- In the decision of reversal, in the face of the fact that the defendant Turkish Aeronautical Association’s attorney stated that an eviction lawsuit was filed by his client against the plaintiff tenant before the case at hand based on the eviction undertaking subject to the case at hand, which resulted in acceptance and the decision was finalized; it was pointed out that the case file related to the eviction case should be brought and the issue of whether the decision made in that case would constitute a final judgment or conclusive evidence or strong discretionary evidence in terms of the case at hand should be evaluated.

In the justification of the decision of the Local Court subject to appeal, it is stated that the decision rendered in the eviction case will not constitute a final judgment in the case at hand, since the parties, subject matter and reasons of both cases are different.

In this case, the decision subject to appeal is not a decision of resistance in reality; it is a new judgment formed by taking inspiration from the reversal and making an evaluation in line with the reversal.

Therefore, the duty to review the judgment on appeal belongs to the Special Chamber, not the General Assembly of Civil Chambers.

CONCLUSION : 1- For the reason explained in subparagraph (1) above, the appeal petition of the plaintiff’s attorney is rejected;

2- For the reason explained in subparagraph (2) above, it was unanimously decided on 27.02.2008 to send the file to the 11th Civil Chamber for the examination of the appeal objections of the attorneys of the defendants against the new judgment.

 