General Assembly of Law 2017/1611 E. , 2018/1128 K.
“text of jurisprudence”
COURT : Court of First Instance
At the end of the trial held due to the “Decommissioning and registration of title deeds” case between the parties, Hatay 1. The date given by the Civil Court of First Instance for the acceptance of the case is 20.12.2012 and 2009/129 E., 2012/652 K. the numbered decision is being appealed by the defendant land owners’ attorney and the defendant contractor’s attorney, the Supreme Court Dec. 23. The date of the Law Office is 04.10.2013 and 2013/3932 E., 2013/6077 K. with the numbered decision,
“…The plaintiff’s attorney, the defendants in return for a share of land that exists between a construction contract, the contractor pursuant to the agreement between the defendant and the plaintiff, plaintiff’s common to construction costs, but the parts that are falling stock when construction is finished to the contractor setting forth whether the plaintiff has been transferred to independent half by land and half in the case statement of independent parts that are reported cancel the registration request and registration of shares on behalf of the plaintiff has prosecuted.
The defendant … attorney, the plaintiff did not fulfill his actions in accordance with the protocol; the other defendant land owners attorney, Decisively arguing that the defendant contractor did not fulfill his actions, have requested the dismissal of the case.
Court, the prosecutor, the defendant is subject to the provisions of the protocol between the contractor assignment of the claim where the plaintiff and the defendant the plaintiff’s land that the owners can take that too far on the grounds that the repository for missing work, the case of the defendant the amount of storage it was decided to acceptance and payment.
The decision was appealed by the defendants’ attorneys.
A construction contract was drawn up between Decedents … and other Decedent land owners in exchange for a land share dated 07.08.2007, and the stages of the Decommissioning of independent sections that will hit the contractor were also determined in the contract. Subsequently, an ordinary partnership agreement was signed between the plaintiff and one of the defendants in accordance with the legal nature dated 08.08.2008 and it was decided to carry out the construction Decisively together. In the said contract, the land owners are not parties, but the addressee of the land owners is the Decedent, the person to whom they can make a claim and to whom they have fallen into debt……….. is the Decedent……….. In the case at hand, since the ordinary partners are asked by the plaintiff … Dağlı to register shares in the independent sections that are claimed to be given to him, and it is understood that their land registry records are still on the land owners, there is no illegal aspect for the land owners to take part in the case. Dec.11, Dec.11, 2018, there is no illegal aspect for the land owners to take part in the case.
In that case, work to be done by the court, in the case cancel and claim deed being registered in the case of the independent departments, the defendant by the contractor 07.08.2007 land owners a hard time in return for a share of plot qualify it being determined according to the provisions of the construction contract as to whether or not the aforementioned as a result of the evaluation in accordance with the contract, the defendant’s rightful independent contractor, there is a section; in this case, in accordance with the contract dated 08.08.2008 between the plaintiff and the defendant contractor, it consists in investigating and evaluating whether the conditions for the claimant’s claim have been formed and Decisively reaching a decision appropriate to its conclusion.
Without taking into account the mentioned issues, with an erroneous interpretation, the acceptance of the legal relationship between the plaintiff and the defendants … as the assignment that you will receive, and the establishment of a written judgment with incomplete examination was not correct, the decision had to be Decertified, … ”
the court resisted the previous decision at the end of the trial, which was overturned on grounds and turned back to the file instead.
DECISION OF THE GENERAL ASSEMBLY OF LAW
The law was examined by the General Assembly and after it was understood that the decision to resist was appealed during the period and the documents in the file were read, the necessity was discussed:
The case is related to the cancellation of the title deed and the registration request.
The plaintiff’s attorney, the defendant, with the other defendants who are owners of land between the contractor 07.08.2007-time plot in return for a share of the construction contract that was signed according to the contract, the construction will be performed by the contractor, and in return, Apartment 8, provision was agreed on, the completion of construction, 1, 2, and No. 6 with the client that the defendant sold and the apartments were transferred to the new owners signed between the contractor 08.08.2008-time protocol client according to the plot with the contractor in accordance with the construction contract was signed between the owners of the plot in return for share, the defendant must be given to the contractor 1, 2, 6, 7, 8, 9, 10 No. 11 All rights and obligations of the apartments and the apartments are entitled to be joint with Malik than or equal to the client to the contractor for the construction of 136.605,00-TL paid, but the defendant in violation of the provisions of Protocol 1, 2 and 6, the price of the apartments in the sale of his client to the contractor that it did not fall into independent sections will be left at a rate of ½ citing registration, the right to request that was born, he requested and sued to Decisively register the half-share of the apartments numbered 7, 8, 9, 10 and 11, which will be given to the contractor in the Decisively completed building in accordance with the construction contract in exchange for the land share signed between the defendants, on behalf of the plaintiff.
The contractor’s representative, the defendant, his client with other land owners of land between the defendant in return for a share of the client that the construction contract was signed, construction began on the portion of basic shelter after it is finished, the plaintiff accepted the offer of his client partnership, and the partnership with the protocol on 08.08.2008 that it was the plaintiff, the plaintiff will be made from the date of ½ percent of all expenses and revenues 8 of the protocol that they have in common. paying paid amounts paid to him, refraining from paying, the claim that he paid 136.605,00-TL is not true, his client significantly completed the construction in accordance with the contract he made with the land owners, he defended the dismissal of the case, asking for a decision on the registration of ¼ share of the independent sections subject to the case on behalf of the plaintiff with his petition dated Dec 21.06.2010.
The defendant, the deputy of the land owners, defended the Decommissioning of the case.
The court acts in accordance with the construction contract in return for a share of the contractor are met if the plot would dig individual rights, personal rights on the basis of this independent ownership of land left to him from the owner could ask for parts that are to be written in the name of the registration or the consent of the owner of the plot with the condition and assign to third parties without the consent of the personal rights that can both land and the contractor against the owner of the third person need to possess the right one could argue that it is personal, and the registration of ownership in the name of independent parts could ask for, land owners in return for a share of land between contractor and in accordance with the construction contract, the contractor should be given to himself, which is registered on behalf of the owner of the plot but still, 7, 8, 9, 10 and 11. independent, such as the registration on behalf of the department may request, according to the provisions assignment of claim, the plaintiff’s or the contractor’s rights and are considered to be the successor of that can argue against other defendants, the defendants on behalf of the owner of the registered land 7, 8, 9, 10 and 11. independent sections with the cancellation of the deed of record and registration in the Land Registry on behalf of the plaintiff stock ½ , it was decided to transfer the remaining shares on behalf of the Decedent land owners.
Upon the appeal of the defendant contractor’s attorney and the defendant land owners’ attorney, the decision was overturned by the Private Decisionon the grounds described in the title section above.
By the Local Court in addition to the previous reasons, the contractor who gained against other defendants are the owners of the personal rights that partially conveyed to the plaintiff, the code of obligations numbered 818 and the continuation of this situation 162 assignment of claim to be made in accordance with the articles of the nature of the case the plaintiff fulfilling the contractor’s liability arising from the cancellation of the deed and the registration is related to the request, the contractor had fulfilled its contractual obligations to the holders of the plot of the investigation in this case is not the issue as to whether, the other defendant with the defendant contractor of a mismatch between the owners of the land in the absence of such evidence, Private apartment where research is performed as specified in the decision of the prosecutor, the defendant contractor’s 07.08.2007-time they deserve the independent sections are determined according to the provisions of the contract and according to the results, it was decided to resist on the grounds that its decision has been given.
The decision to resist was Decisively appealed by the defendant contractor’s attorney and the defendant land owners’ attorney.
The dispute that came before the General Assembly of Civil Law through resistance: whether the plaintiff can request the registration of ½ share of the immovable property registered in the title deed on behalf of the land owners in accordance with the assignment provisions that you will receive according to the protocol dated 08.08.2008 with the contractor, whether the plaintiff should investigate whether the conditions for making a claim from the land owners have occurred and Dec Decisively decided on the basis of its result.
First of all, it is useful to focus on the “work contract” and “construction contract for land share” and “debts of the contractor and the Deckh Deckholder:
The work contract is governed by Article 355 of the abrogated Code of Obligations No. 818 (UK), which must be applied in the resolution of the dispute. (470 of the Turkish Code of Obligations (TCO) No. 6098. the exception is a contract in which one party (the contractor) undertakes to produce something in exchange for the semen that the other party (the owner of the business) undertakes to give. it is described as “.
As a rule, the Turkish Code of Obligations No. 6098 (6098 p. TBK) 470. in the article (818 p. TALK., m. construction construction contracts, which are a type of work contract defined in Article 355), are contracts that impose debts on two parties that include mutual actions in exchange for the transfer of land shares. Dec.
The main debts of the contractor in construction contracts are the debts of creating a construction (work) and delivering this work to the owner of the work. A number of other side debts arising from these two main debts and ensuring the performance of these debts in accordance with the contract are the good performance of the work, the duty to do the work faithfully and carefully in relation to the preparation of the work in accordance with the contract, debts related to tools and materials, general notification obligation, the duty to start and continue work on time, and the debt of takeffül against the defect, which is an important debt arising from it (Karataş I; Eser (Construction Construction) Contracts, Ankara 2009, p.99).
When the contractor fulfills the acts arising from the construction contract, he/she gains personal rights against the land owner and may request the land owner to transfer the title deed of the independent sections left to him/her in accordance with the contract to his/her name. Dec. Dec. Pursuant to Articles 162 and Dec. of the UK, he may transfer and assign this personal right to third parties on condition that it is in writing without the need to obtain the consent and approval of the land owner.
In such contracts in exchange for the specified debts of the contractor, the business owner also owes paying a price as a Decisional act by “transferring the land share” in exchange for the work performed on the land Decisively. In these contracts, the fee (price) to be paid by the business owner is paid by the owner of the land as the month. Dec. Due to the fact that such contracts are usually spread over many years, it is not possible to achieve the purpose of the contract by fulfilling this single fee act during the performance period. For this reason, some ancillary debts must also be fulfilled by the business owner. These; suitable for the construction of a barrier on the land without legal and actual delivery without defect and of the land of obtaining the zoning and building permits, plans and projects in municipalities with their approvals to the Competent Authority of the contractor’s rightful independent finance the sales floor easement deed of partition for the supply of the establishment of the intake housing permits as needed for business and operations of the contractor, such as a power of attorney to be given a share of land specified in the contract, such as the transfer of liabilities.
As a rule, in the types of contracts that impose a debt on both parties, if one of the parties does not have an obligation to make a statement in advance, the debtor who does not perform his own performance will not be able to request the other party to perform his performance (Kılıçoğlu A.M: General Provisions of the Law of Obligations, Ankara 2012, p.581). This is part of BK 81. in the article “A person who requests the performance of a contract with the content of reciprocal commitments must have fulfilled his debt or offered to perform his performance, unless he has the right to benefit from a deadline in accordance with the terms and nature of the contract”, the same issue is regulated by the supervisor’s provision, 97 of the TCO. it is also subject to judgment in the article.
However, the right is personal to him and the contractor, in writing, appropriation, which his successor, the third person of this right in order to argue against the land owner, as mentioned above, the act must be fulfilled the contract, the contractor installs itself exactly (Izzet Karataş, work contracts, 2004, s. 34 et seq.).
Since construction construction contracts for land share are also types of contracts that impose debts on both parties, the order of performance, that is, the question of which of the parties will be obliged to perform Decisively first, is important. In this kind of contracts, the contractor party, which is under the obligation to build the building first, must perform its performance in accordance with the contract, and then request the Deckhouse owner to perform his performance. In other words, first of all, the work should be done in accordance with the contract, then the owner of the land should be requested to perform his Decency.
The owner of the land plot may perform the Decommissioning of the Decommissioning share in different ways. This act can be performed either by transferring the transfer of the agreed land shares to the contractor when the construction is completed, or by Decisively transferring the title deed according to the stage at which the construction has come in the contract. In this second case, that is, in the gradual transfer of title deeds, the contractor has the right to request the Decommissioned deeds from the land owner at each stage.
As a matter of fact, the same principles were adopted by the General Assembly of Law on the day of 24.02.2016 and 2014/23-724 E., 2016/168 K., the day of 26.02.2016 and 2014/23-569 E., 2016/181 K. it is also emphasized in the numbered decision.
When these explained material law rules are evaluated by presenting the concrete event;
Hatay 2 between Decedent contractor and other Decedent land owners. The construction contract was signed by the notary’s office on Dec. 07.08.2007 and numbered 12425 days in exchange for the land share. According to the contract, it was decided to build a basement, a Decking and a block consisting of three normal floors according to the project and the attached sketch to be drawn in accordance with the plan and project to be produced from the local municipality and science works on the immovable lot No. 7337 in Çekmece village of Antakya province of Hatay registered on behalf of the land owners. Upon completion of construction by the contractor, ground floor, 1/3 of the circle No. 2 on the first floor, 3, 4 and 5 will belong to the owners of all the land on the regular units, the remaining 2/3 of the circle and second layer No. 2, Ground Floor, 6, 7 and 8 located on the third floor apartments, duplex apartments apartment 9 No. 10 No. 11, and will belong to the contractor.
12 Of the contract. according to the article, the project cost, building-inspection, municipal related project expenses, floor easement fees, land registry related fees, insurance premium costs, material costs, work and labor costs will belong to the contractor.
In addition, the contract regulates when the independent sections will be gradually transferred to the contractor during the construction phase of the construction.
A protocol dated Dec 08.08.2008 has been issued between the contractor and the plaintiff. According to the protocol, it was decided that the plaintiff should share all the obligations assumed by the construction contract with the land share of Dec Dec 07.08.2007 signed by the contractor with the land owners in half, and equally share the rights and responsibilities.
Protocol 7. according to the article, it is stated that if the plaintiff fulfills his Decency in accordance with the protocol, he will be the owner of half of the independent sections to be given to the contractor, and the contractor will benefit equally from all the rights and benefits that he will receive from the construction contract in exchange for a land share, as in debt and liability.
Additional received by the court dated 07.05.2011 the expert’s report, the construction contract was signed between the contractor and the owners of the land plot in return for share of the cost of work completed construction made in accordance with 3.700,00-TL is the balance of the service fee 14.957 building inspection,00-TL determined that it was still not paid. In the expert report dated 11.05.2012 received from the financial advisor expert, it was determined that the defendant contractor did not pay the SSK premium of 19.616,68-TL within the scope of the construction carried out.
In the letter of Hatay Tax Department dated 20.07.2012, it is stated that the defendant contractor has a tax debt of 6.463,29-TL due to the construction work activity as of 01.03.2008.
According to the protocol dated Dec 08.08.2008 signed with the plaintiff, the defendant contractor has undertaken to transfer half of the independent sections that will fall to him in accordance with the construction contract for the land share dated Dec 07.08.2007 signed with the defendant land owners to the plaintiff based on his personal right. However, in order for both the contractor and the plaintiff, who has inherited his personal right from him in writing, to assert this right against the Decedent land owners, it is imperative that the contractor has fully fulfilled the performance imposed on him by the contract.
For the reasons discussed, the court primarily the owners of the plot of the contractor 07.08.2007-time plot in return for a share according to the terms of the construction contract of the case, determining whether they deserve it or not subject to independent sections, the part that deserves an independent contractor if the contractor signed with the plaintiff that the defendant 08.08.2008-time to claim the independent section of the protocol in accordance with the provisions of the requirements should be decided according to the results of the quantification are investigated these issues have not been observed, missing, review and evaluation, the provision has been established.
In this case, according to the mutual claims and defenses of the parties, the minutes and evidence in the file, the reasons explained in the decision to overturn the decision to overturn the Special Chamber adopted by the General Assembly of Law, while it is necessary to comply with the previous decision, it is contrary to the procedure and the law to resist.
The decision to resist for the reasons described should be overturned.
CONCLUSION: For the reasons described above, the defendant contractor and the defendant land owners attorney’s decision to resist with the acceptance of the appeal objections of the reasons shown in the decision to Decriminalize the Private Apartment Provisional 3 of the Code of Civil Procedure No. 6100. 429 of the Code of Civil Procedure No. 1086, which is applied according to Article. in accordance with Article 440 of the same Law, in case of request, the appeal advance fee is returned to the depositor. according to the article, the decision was made unanimously on the day of 23.05.2018, with the way to correct the decision being open within fifteen days from the notification of the decision.